Upcoming Capital Projects
Houston Airports has a five-year capital improvement program (CIP), approved by the City of Houston City Council, which calls for $2.5 billion of spending through fiscal year 2025. The capital improvements are concentrated in terminal and airfield projects with the majority dedicated to George Bush Intercontinental Airport. An updated CIP is approved annually by the Houston City Council as part of each new fiscal year. This CIP was approved on June 24, 2020 by City Council.
Click here to download the latest Houston Airports 5-Year CIP summary.
Upcoming CIP Projects
Project No | Location | Phase | Project Description | Estimated Date | Estimated Budget (000) |
---|---|---|---|---|---|
546 | IAH | DB | UPGRADE & RELOCATE APM FACILITIES | 1/1/2022 | 29,870 |
546A | IAH | C | APM FACILITIES - REPLACE 2 CARS | 10/1/2023 | 14,632 |
604A | IAH | C | SUBWAY DESIGN | 3/1/2022 | 33,575 |
618A | IAH | C | TUNNEL DRAINAGE IMPROVEMENTS (WATER ISSUES) | 8/1/2021 | 2,318 |
646A | IAH | C | TAXIWAY RA,RB,SA,SB - CONSTRUCTION (Phase 1,2 & 3) | 6/1/2021 | 65,632 |
653 | HOU | C | NORTH ELECTRICAL UPGRADES | 6/1/2024 | 5,217 |
668 | IAH | C | REHABILITATE & EXPAND ARFF STATION 92 | 1/1/2022 | 12,000 |
669 | HOU | C | REHABILITATE & EXPAND ARFF STATION 81 | 6/1/2022 | 11,880 |
672 | HOU | C | HOBBY DRAINAGE - ROADWAY FLOODING | 7/1/2025 | 3,342 |
673 | IAH | DB | TERMINAL A MODERNIZATION PROGRAM | 12/1/2021 | 242,800 |
673A | IAH | C | TERMINAL A OUTBOUND BHS OPTIMIZATION - (Phase 1, 2 & 3) | 12/1/2020 | 37,062 |
673B | IAH | C | TERMINAL A DOMESTICE EXPANSION | 10/1/2021 | 261,000 |
673C | IAH | DB | TERMINAL A EARLY & ENABLING | 3/1/2022 | 43,000 |
673D | IAH | C | TERMINAL A AIRLINE (CARRIER) RELOCATION | 3/1/2022 | 9,000 |
686 | IAH | C | IAH STORM WATER POLLUTION CONTROL SYS - ENVIRON LIFT ST | 7/1/2021 | 22,603 |
733 | EFD | C | T-HANGER RAMP AND TAXIWAY D PAVEMENT REHAB | 7/1/2025 | 1,463 |
735A | IAH | C | IAH EXIT LANE TECHNOLOGY - MULTI -YEAR | 7/1/2025 | 1,580 |
735B | HOU | C | HOU EXIT LANE TECHNOLOGY - MULTI-YEAR | 7/1/2025 | 1,596 |
770 | HOU | C | HOU NON-STANDARD FAA TAXIWAYS | 3/1/2021 | 27,843 |
770B | HOU | C | EARLY DEMOLITION OF 17/35 PAVEMENT | 12/1/2020 | 9,751 |
773 | HOU | C | TAXIWAY M REHAB | 7/1/2023 | 16,298 |
775B | HOU | C | RELOCATION OF TSA & HPD BUNKER & K9 | 7/1/2021 | 3,100 |
784 | HAS | C | PUBLIC WI-FI EXPANSION INTO CONCESSION AREAS | 12/1/2020 | 3,296 |
793 | HAS | C | IAH AIRPORT OPERATIONS CENTER | 2/1/2022 | 3,387 |
794C | HAS | C | TERMINAL C & TERMINAL C GARAGE WAYFINDING | 1/1/2021 | 4,945 |
822 | IAH | DB | ENABLING UTILITIES - LANDSIDE | 7/1/2021 | 41,661 |
826 | IAH | C | MLIT - TERMINAL, AIRSIDE, LANDSIDE | 12/1/2020 | 296,595 |
828 | IAH | C | FIS CAPACITY EXPANSION | 7/1/2021 | 387,717 |
907 | IAH | C | REHABILITATION OF TAXIWAY NA | 11/1/2020 | 25,000 |
907 | IAH | C | REHABILITATION OF TAXIWAY NA | 9/1/2021 | 25,000 |
921 | HOU | C | HOBBY CONRAC - PLANNING DESIGN CONSTRUCTION | 7/1/2021 | 203,683 |
922 | IAH | C | ARFF AFFF COLLECTION FACILITY | 1/1/2022 | 7,787 |
927 | HOU | C | HOBBY VEHICLE FUELING STATION | 1/1/2022 | 1,086 |
931 | IAH | C | IAH FLYOVER BRIDGE RECONSTRUCTION (RP) | 2/1/2021 | 8,500 |
932 | HOU | C | 7 GATE EXPANSION AT HOBBY | 1/1/2022 | 234,000 |
933 | IAH | C | TERMINAL B PHASE III APRON | 7/1/2023 | 176,500 |
934 | HOU | C | RECONSTRUCT TAXIWAY C AT HOBBY | 7/1/2023 | 37,000 |
935 | IAH | C | CONSTRUCTION OF KENSWICK INTERSECTION | 7/1/2021 | 3,000 |
936 | HOU | C | HARDEN AOA PERIMETERS | 7/1/2022 | 2,000 |
937 | HOU | O | CCTV UPGRADES AT HOBBY AIRPORT - IT (R&R) | 2/1/2021 | 1,200 |
A420 | HOU | C | AMS-TAXIWAY G, K, K1 , K2, L & R REHAB AT HOBBY AIRPORT | 7/1/2023 | 7,439 |
A432 | HOU | C | PASSENGER CONVEYANCE SYS, FIRE PROTECTION SYS, HVAC & UTILITIES REHAB AT HOU | 7/1/2024 | 6,614 |